Grout placed where still columns will go, gives a buffer area between the base plate and the concrete footing. Giving a flush connection.


Steel Columns are placed with the use of cranes to lift and lower onto the starter bars.
Nuts are used to hold the Steel column to the ground as large forces from the roof and walls travel through these columns.
Posted by A.J.Edwards at 5/29/2007

No comments:

Post a Comment

Newer Post Older Post Home
Subscribe to: Post Comments (Atom)

Archives

  • ▼  2007 (26)
    • ▼  May (25)
      • Major Project Model
      • Major Project Development 5
      • Major Project Development 4
      • Major Project Development 3
      • Major Delevlopment 2
      • Major Project Development 1
      • Advanced Steel Construction
      • Millions at stake as towers left up in the air
      • $500m park landing at Essendon Airport
      • CityLink caned on toll road
      • Union blames Comcare for crane incident
      • How Steel Is Made.
      • Construction workers could boycott Blundstone boots
      • Victoria's construction industry gives value for m...
      • Portal Frame Under Construction
      • Portal Frames
      • Why Use Steel ???
      • Trip To Bunnings
      • Wall Section
      • Attempt 1 at end capFinal Attempt
      • Gutter
      • Gutter Section Attemt 1Gutter Section Final Attempt
      • Section A-A
      • Attempt 1 at Box Gutter SectionFinal Attemt at Box...
      • Attempt 1 of Portal FramesFinal Attempt
    • ►  March (1)

About Me

A.J.Edwards
Uni student at deakin.Studing Construction Management. Check Out www.victoriantigers.com.au
View my complete profile