Tuesday, May 29, 2007
Major Project Model
First Image showing the workings of the reinforcement under the column and slab the second showing the the final product.
Major Project Development 5
Grout placed where still columns will go, gives a buffer area between the base plate and the concrete footing. Giving a flush connection.
Steel Columns are placed with the use of cranes to lift and lower onto the starter bars.
Nuts are used to hold the Steel column to the ground as large forces from the roof and walls travel through these columns.
Steel Columns are placed with the use of cranes to lift and lower onto the starter bars.
Nuts are used to hold the Steel column to the ground as large forces from the roof and walls travel through these columns.
Major Project Development 3
Major Delevlopment 2
Major Project Development 1
Subscribe to:
Posts (Atom)